Project: Cherrywood Residential

Cherrywood Residential

Using FasterFix Modular Rebar, the project team installed 16 tonnes of reinforcement across a 117m² foundation
in just six hours with four fixers.
Compared with a typical loose-bar installation programme of approximately three working days, this represents
an estimated 64% reduction in installation time, enabling earlier progression to the next construction phase while
improving site efficiency, reducing manual handling and maintaining quality throughout the installation process.

Client

John Paul Construction

Problem

Aggressive Time Deadlines and Difficult Conditions

Solution

FasterFix Modular Rebar

Project Details

Based on typical industry productivity for traditional loose-bar installation, the equivalent work would generally take approximately 3 working days. This represents an estimated 64% acceleration in installation time

Number of onsite Fixers

4

Tonnage

16 tonnes