Project: DUB10 Data Centre

DUB10 Data Centre

This job was complete in 6 hours with just 2 fixers and over 23 tonnes were installed.

This is what the future of rebar looks like with full traceability, digital integration and consistent product quality.

Client

Walls Construction

Problem

Aggressive Time Deadlines

Solution

Fasterfix just in time service 

Project Details

Fast track data centre builds during need for rapid technology advancements, 23 tonnes of FasterFix installed in 6 hours. Concrete poured 6 days after we received the design intent to start detailing.  

Number of onsite Fixers

4

Tonnes

93