Project: FasterFix Modular Retaining Wall

FasterFix Modular Retaining Wall

A modular retaining wall installed for our valued client Liam Neville Developments Ltd by a team of 3 fixers, base and starter bars completed on day one, full wall panels in place by the end of day two.

Client

Liam Neville Developments

Problem

Aggressive Time Deadlines and Difficult Conditions

Solution

FasterFix Ready Wall System

Project Details

A modular retaining wall installed by a team of 3 fixers, base and starter bars completed on day one, full wall panels in place by the end of day two.
10 hours total on site. No delays waiting on material. No waste. Just a clean, efficient install from the ground up.

 

Number of onsite Fixers

3

Tonnage

8 tonnes

 