Project: Intel Leixlip  

Intel Leixlip  

26,000 tonnes of offsite reinforcement delivered over 18 months. At peak, this project took up to 21 arctic loads per day of prefabricated rebar modules.  

Client

BAM

Problem

Because the project was on such a large scale the program schedule was uncertain.  A low availability of steel fixing labor 

Solution

FasterFix just in time service 

Project Details

Intel new microchip factory in Leixlip,  

Pad foundations/Trench bases/Slab on grade, suspended slabs, waffle slabs all prefabricated off site and delivered just in time 

Our team achieved the installation of a 600 tonne raft slab in 5 days, and a 200 tonne raft slab in a day and a half, using FasterFix 

Tonnes

26,000

Contact Us