3-meter-deep beams with intricate detail were placed in 6-meter sections against the tide allowing the project to be delivered ahead of program.  

Client

BAM

Problem

Working against the tide on a tight program 

Solution

Prefabricated sections being dropped in the time zones allowed by the tide 