Project: Ringaskiddy Port  

Our biggest project so far:

18 Months

26,000 Tonnes

Total Offsite Solution

Ringaskiddy Port  

3-meter-deep beams with intricate detail were placed in 6-meter sections against the tide allowing the project to be delivered ahead of program.  

Client

BAM

Problem

Working against the tide on a tight program 

Solution

Prefabricated sections being dropped in the time zones allowed by the tide 

Project Details

Port of ringaskiddy berth expansion   

Number of onsite Fixers

5

Tonnes

400

Number of Beams

Contact Us
Ringaskiddy

Choose Faster Fix For Your

Need a short summary here to go with the CTA

Find Out More