Project: Belvedere College 

Belvedere College 

MS were contracted to do the rebar using FasterFix and deliver the concrete frame itself which was a fair face finish in the whole project. 

Our rebar and formwork/concrete teams delivered the project on program after starting 6 weeks late 

Client

Clancy Construction 

Problem

6 weeks late starting 

Solution

Full package completed by MS concrete and rebar 

Project Details

Belvedere college school across from temple street hospital 

6 floors of fair face concrete finishes. 

Number of onsite Fixers

3

Tonnes